Hi Panigrahi,
Regarding your concern, you can review the forum's AI-suggested answer, as it provides accurate information.
Microsoft Project can store multiple baselines, including Baseline and Baseline 1 through Baseline 10, and each baseline has separate Start and Finish fields. The custom report usually references a different baseline field from the one displayed in the Gantt Chart. For example, the Gantt Chart displays Baseline1 Start / Baseline1 Finish, but the custom report still uses Baseline Start / Baseline Finish.
To resolve this issue, please follow these steps:
- Open View > Gantt Chart > add the following columns:
- Baseline Start
- Baseline Finish
- Baseline1 Start
- Baseline1 Finish
- Check which baseline contains the revised dates.
- Go to Report > Custom > open the affected report > select the report table/chart > open the Field List.
- Make sure the report uses the same baseline fields shown in the Gantt Chart. For example, if the revised dates are stored in Baseline 1, use:
- Baseline1 Start
- Baseline1 Finish
- Close and reopen the report to refresh it.
- If the revised dates do not appear in any baseline fields, update the baseline through Project > Set Baseline > Set Baseline and select the appropriate baseline.
Please note that changing only the Gantt bar formatting does not update the underlying baseline data used by reports.
I also recommend keeping the original plan in Baseline and saving an approved revised plan in Baseline 1, rather than overwriting the original baseline.
Hope this information is useful. Should you have any further questions, please feel free to share them in the comments below. I'm very happy to help.