Microsoft project management software used to plan, manage, and communicate a project schedule and other information among workgroup members, project managers, and other stakeholders.
Stuart Galt,
Doesn't "behave" as you expect. Well, when I set up a custom calendar for a 7.5 hour workday, a 5 "day" task starting Monday 8:00 AM actually finishes at 4:30 PM the following Friday, not the following Monday. So, let's take a deep dive into how you set things up.
- Please show us a screen shot of your "Change Working Time". It should look something like this although your working times may be different. For convenience, I just lopped 30 minutes off the end of the workday.
- Now show us a screen shot of, File > Options > Schedule group. It should look something like this. Note the Hours per day. The Hours per week is only relevant if you are entering duration values in weeks.
- Show us a screen shot of Project Information. It should look something like this:
- Finally, please show us a shot of your Gantt Chart view. It should look something like this:
If what you have set up varies markedly from what I've shown, then you have a clue is to why MS Project is not "behaving as you expect".
Oh by the way, you should go to File > Options > General tab and select a Date format that includes the time.
John