In MS Project the "Change Working Time" facility does strange things

Anonymous
2025-06-10T00:36:16+00:00

My MSP plan works great when I have the project setup on a 7.5hr working day = 37.5hrs per week. However, when I change the working day to be different length (eg 6hrs or 8hrs) MSP no longer behaves as I would expect.

When setup for a 7.5hr day, a 5 day task starting on Monday finishes the following Monday, exactly 1 week later. This is as I would expect. The three 5 day tasks in succession take exactly 3 weeks to complete.

However, when I use the "Change Working Time" facility to change the working day to 6hrs / 30hrs per week, all the previous 5 day tasks now take 6.25 days (they are setup as Fixed Duration). When I adjust the 6.25days back to 5 days to make it correct on all three tasks, suddenly the three weeks of work completes on a Wednesday after 2.5 weeks. This is not the behaviour I expect - I want the days to be 6 hours long and hence 5 days is 30 hours == 1 entire week from Mon to Fri.

NOTE: We are using 6 hours as this has been determined the amount of time 1 engineer will give to a single project when they work 100% on it. The rest of their day is considered an overhead to the company.

Microsoft 365 and Office | Project | For business | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments
Answer accepted by question author
John Project 49,720 Reputation points Volunteer Moderator
2025-06-10T01:56:14+00:00

Stuart Galt,

Doesn't "behave" as you expect. Well, when I set up a custom calendar for a 7.5 hour workday, a 5 "day" task starting Monday 8:00 AM actually finishes at 4:30 PM the following Friday, not the following Monday. So, let's take a deep dive into how you set things up.

  1. Please show us a screen shot of your "Change Working Time". It should look something like this although your working times may be different. For convenience, I just lopped 30 minutes off the end of the workday.

  1. Now show us a screen shot of, File > Options > Schedule group. It should look something like this. Note the Hours per day. The Hours per week is only relevant if you are entering duration values in weeks.

  1. Show us a screen shot of Project Information. It should look something like this:

  1. Finally, please show us a shot of your Gantt Chart view. It should look something like this:

If what you have set up varies markedly from what I've shown, then you have a clue is to why MS Project is not "behaving as you expect".

Oh by the way, you should go to File > Options > General tab and select a Date format that includes the time.

John

Was this answer helpful?

0 comments No comments

3 additional answers

Sort by: Most helpful
  1. Anonymous
    2025-06-11T00:44:00+00:00

    The big "light bulb" moment for me, thanks to your input, was that the settings in "Project Options" under "Change Working Time", specifically the 'Hours Per Day', 'Hours Per Week' and 'Days Per Month', were just conversion factors and don't actually change the project.

    I wanted to change the project by re-defining the length of a working day and these settings were not what I was looking for - all they do is define how MSP converts a user's input of "1d" or "1w" or "1m" to hours when entering planning data.

    I would imagine that many people have made this same mistake, but it seems very obvious to me now that I know otherwise. I don't think it helped that the existence of the "Work Weeks" tab wasn't obvious either (at least, not to me in the way my desktop displays) so it was actually easier to find those other options first of all and assume that they were the ones I needed.

    Seems so obvious now but I simply couldn't figure it out myself! Thanks again

    Was this answer helpful?

    0 comments No comments
  2. John Project 49,720 Reputation points Volunteer Moderator
    2025-06-10T13:28:16+00:00

    Stuart Galt,

    You're welcome and thanks for the feedback. New users of Project often get tripped up with calendars and how it all plays with Project's scheduling engine.

    John

    Was this answer helpful?

    0 comments No comments
  3. Anonymous
    2025-06-10T03:26:58+00:00

    Thanks you John - your helpful reply helped me solve my problem.

    I had "Change Working Time" setup the same as you, but what turned out to be the problem was the settings in the default work week calendar I was using - in your case that's the one called '7.5 hr days'

    It's not obvious in "Change Working Time", but if you click on the "Work Weeks" tab then the "Details" button is no longer greyed out and you can edit it. My calendar was set to 8 hour days in here regardless of what I setup in the front page in "Change Working Time".

    Was this answer helpful?