Tim Schereck,
Sorry, Project doesn't work that way. The option settings for a "day" or "week" are singular, that is they are independent of any calendar. The only way to get duration values that are applicable to any calendar is to enter hours in the Duration field.
Yeah, I know, bummer, but that's the way Project has worked from day 1.
Hope this helps.
John