Hi All,
I have two SSAS cubes:
1.Cube C1 with measure m1, writeback enabled partition
2.Cube C2 with measure m2
I have created cube C3 with two linked measure groups: C1 (measure m1) and C2 (measure m2).
In cube C3, I have created calculated measure called m1_m2 with MDX definition: [Measures].[m1] + [Measures].[m2]
In Excel users write new data to measure m1 (cube C1) and deploy changes. Writeback is committed.
New data are immediately in cube C3 measure m1. But calculated measure m1_m2 is not changing. Measure m1_m2 still shows value before deploy changes by users. It looks like calculated measure m1_m2 has data from cache, that is not updated after writeback operation.
Calculated measure m1_m2 has correct value, when I clear cache by query:
<ClearCache xmlns="http://schemas.microsoft.com/analysisservices/2003/engine">
<Object>
<DatabaseID>DEMO</DatabaseID>
</Object>
</ClearCache>
What should I do, to help my users have correct value m1_m2 after deploy changes.
Please help me.
Many Thanks!!