Hi Low,
Thank you for your question.
Planner Premium supports advanced task dependencies, but these dependencies are limited to tasks within the same plan. At this time, there is no built-in option to create a direct scheduling dependency between tasks in separate Premium plans.
As a workaround, you could consolidate the related tasks into one Premium plan and use buckets, summary tasks, milestones, or custom fields to separate the different projects or workstreams.
For reference, you may find these articles helpful:
- Advanced capabilities with premium plans in Planner
- Compare Microsoft Planner basic vs. premium plans
If cross-plan dependencies are important to your workflow, you may also consider submitting this suggestion through the Planner Community. This will allow the product team to review the request for possible consideration in future updates.
I hope this helps clarify the current functionality. Should you have any further questions or need additional assistance, please feel free to share them in the comment below. I'm very happy to help.
Additionally, since many other users have expressed similar concerns but may not know where to submit feedback, if my response has helped you better understand the situation and guided you toward a possible next step, please mark it as 'Yes'. Your action will help pin this post to the top, making it easier for others in the community who are experiencing the same issue to find your feedback and support it.