Microsoft project management software used to plan, manage, and communicate a project schedule and other information among workgroup members, project managers, and other stakeholders.
Enter the task duration with the elapsed-day suffix, such as 7ed, when you want Project to count seven consecutive calendar days rather than seven working days.
Use calendar-day durations
- In the Gantt Chart, locate the task’s Duration field.
- Enter the duration using
edinstead ofd:-
7d= seven working days according to the effective calendars. -
7ed= seven elapsed/calendar days, including weekends and other nonworking time.
-
- Press Enter and check the calculated Finish date.
Project also supports elapsed hours, weeks, and months through eh, ew, and emo. Microsoft’s documented example states that 7d can run Monday through the following Tuesday when weekends are nonworking, whereas 7ed runs Monday through Sunday.^1^
There is therefore still a calendar-days option, but it is expressed as an elapsed duration unit, not as a separate Duration setting.
Why changing “hours per day” did not solve it
Project’s normal Duration is the total span of active working time, not simple date subtraction.^2^ Changing Hours per day changes how Project converts a value expressed in days into hours; it does not turn d into calendar-day arithmetic. Those day/week conversion settings are global and independent of a particular calendar.^3^
By contrast, Excel formulas such as FinishDate-StartDate count the difference between date serial values without applying Project’s working-time calendars. To compare like with like:
- Excel calendar-date difference → use
edin Project. - Excel business-day calculation based on a work calendar → use ordinary
dand make Project’s calendar match the Excel assumptions.
If ordinary working-day durations are still inconsistent
For tasks that should observe business hours rather than elapsed time, inspect the effective calendars instead of changing the hours-per-day conversion again:
- Select Project → Change Working Time.
- In For calendar, select the project calendar.
- Review Work Weeks → Details and the Exceptions tab for weekends, holidays, and working hours.
- Select Project → Project Information and verify that the intended project calendar is selected.
- For an affected task, right-click it and select Information → Advanced; check whether it has a task-specific calendar.
Project can combine base, project, task, and resource calendars, and the resulting availability determines the scheduled dates.^4^ A task calendar can also override the project calendar.^5^
Also enable a date format that displays the time, under File → Options → General → Date format. A hidden start or finish time can make two apparently identical dates represent different duration boundaries.^6^
Use a 24 Hours project calendar only when the work itself must be scheduled continuously. For a task that merely needs a fixed calendar-time span while the rest of the project follows normal business calendars, ed is the more targeted choice.^7^
References
- DurationFormat Element
- Duration Element
- Setting Hours per Week for a specific Calender - Microsoft Q&A
- Work with calendars in Project | Microsoft Support
- Create a calendar for a task within Project | Microsoft Support
- In MS Project the "Change Working Time" facility does strange things - Microsoft Q&A
- Set the general working days and times for a project | Microsoft Support