Hi john,
Thank you for sharing the migration details.
Based on the screenshot, the migration has been running for over 70 hours and is currently 78% complete.
While the total data size is only around 65 GB, the source contains more than 66,000 items, which can significantly impact migration performance, especially when many of the files are small.
Additionally, the report shows 25,511 items with scan issues. Since these items appear to be excluded from the eligible migration count, they may not be migrated successfully unless the issues identified in the Scan Summary Report are resolved.
I recommend reviewing the Scan Summary Report (via View Reports) to identify the affected items. Common causes include invalid file names, unsupported characters, excessive path lengths, blocked file types, or permission-related issues.
For the planned weekend cutover, I recommend the following approach:
- Review and resolve as many scan issues as possible before the cutover.
- Complete the bulk migration ahead of the weekend.
- Minimize changes to the NAS during the cutover period.
- Run an incremental migration (delta sync) during the weekend to transfer only new or modified content.
- Use a migration machine with adequate resources and a stable high-speed network connection.
- If feasible, split the migration into multiple tasks to improve throughput.
You may also consider using Migration Manager, which supports multiple migration agents and can help distribute the workload. However, changing tools alone may not significantly improve performance, as migration speed is still affected by source storage performance, network conditions, file composition, and SharePoint throttling.
Although the current estimate shows approximately 16 hours remaining, this may change depending on source performance, retries, network conditions, and service-side processing. Given that the current test has already exceeded 70 hours, completing a full migration from scratch within a strict 72-hour maintenance window cannot be guaranteed.
Therefore, the safest approach would be to pre-stage the majority of the content before the weekend and use the cutover window for the final incremental migration and validation.
For additional guidance, please refer to:
- General migration performance guidance
- Improve SPMT or Migration Manager performance
- Migrate file shares with Migration Manager
I hope this helps clarify the migration behavior and assists with your planning. If you have any questions or concerns, please let me know. I'll be happy to assist further.