Microsoft project management software used to plan, manage, and communicate a project schedule and other information among workgroup members, project managers, and other stakeholders.
In Project Standard for Windows, open the Excel workbook through File > Open > Browse, then use the Import Wizard to map its columns to Microsoft Project fields.^1^
Import the Excel file
- Prepare the workbook in Excel
- Put column headings in the first row.
- Keep the data in a simple table without merged cells or blank heading rows.
- For a basic task list, useful headings include:
-
Task Name -
Duration -
Start -
Finish -
Predecessors -
Resource Names
-
- Save and close the workbook before importing it.
- Open the workbook from Project
- Start Microsoft Project Standard.
- Select File > Open > Browse.
- In the file-selection window, change Files of type to Excel Workbook.
- Select the
.xlsxfile and choose Open.
- Complete the Import Wizard
- Choose New map if prompted.
- Select the option to create a new project unless the spreadsheet is intended to update an existing Project file.
- Select Tasks.
- Select the worksheet containing the task list.
- Indicate that the first row contains column headings, if that option appears.
- Map the Excel columns
On the Task Mapping page, match each Excel heading in the From column with the corresponding Project field in the To column. Example:
The important detail is that Project calls the task-title field Name, not Task Name. If “Task Name” is missing from the Project-field list, select Name instead.^2^Excel column Microsoft Project field Task Name Name Duration Duration Start Start Finish Finish Predecessors Predecessors Resource Names Resource Names - Check the Preview area to confirm that the columns line up correctly, then select Finish. Project’s mapping page also lets you change a destination field, delete an unwanted row, or add fields before completing the import.^1^
- Review the imported schedule and save it as a Project file:
- Select File > Save As.
- Save it as an
.mppfile.
If the result is incorrect
- If tasks appear but names are blank, map the Excel task-name column to Name.
- If dates or durations import incorrectly, simplify those columns in Excel so each column contains one consistent type of value. For duration or work imports, a Microsoft Project Q&A answer notes that Project stores time-related data internally in minutes; this is particularly relevant when raw numeric values are being imported.^2^
- If the workbook does not appear in the Open window, verify that Excel Workbook is selected under Files of type.
- If possible, first test with a copy containing only three columns—
Task Name,Duration, andStart—to make the mapping easier to diagnose.
Getting telephone or live support
A callback cannot be initiated through this Q&A response. For official Microsoft assistance, open the Get Help app from the Windows Start menu, describe the Project import problem, and select Contact Support if offered. Depending on the product, subscription, operating hours, and scenario, the available options may include browser chat or providing a telephone number for a support-agent callback.^3^
References