Live Power BI reporting without manual Excel exports.

Krishna Teja Dinavahi 0 Reputation points
2026-11-12T15:19:52.33+00:00

We are using Microsoft Planner Premium (Project Plan 1).

The plan contains custom task fields such as:

  • Scope (Category)
  • Skill Code (Shop)
  • Task Reference
  • Description
  • Remarks
  • Day Wise Tracking

We connected Power BI to Dataverse and can access standard tables:

- msdyn_project

- msdyn_projecttask

- msdyn_projectbucket

- msdyn_projecttasklabel

However, the custom fields do not appear as columns in msdyn_projecttask and no custom columns are visible in the Project Task Dataverse table.

Please advise:

  1. Where are Planner Premium custom task fields stored?
  2. Which Dataverse table contains these values?
  3. What is the supported method to access these custom fields in Power BI?
  4. Can these fields be accessed via Dataverse, Graph API, or Project APIs?
  5. What is the recommended architecture for a live Power BI dashboard including custom Planner Premium fields?

Environment:

[Moderator note: Personally Identifiable Information removed] (default)

Requirement:

Live Power BI reporting without manual Excel exports.

Microsoft 365 and Office | Project | For business | Other
0 comments No comments

2 answers

Sort by: Most helpful
  1. Kai-L 21,435 Reputation points Microsoft External Staff Moderator
    2026-11-12T15:44:37.1233333+00:00

    Dear Krishna,

    Thank you for the detailed post. You've clearly scoped out what you need, and live reporting without manual exports is a very reasonable goal. Since your questions focus on how Planner Premium custom fields are stored in Dataverse and pulled into Power BI, they go a bit beyond what this forum covers, and I don't want to give you inaccurate guidance on something this important to your reporting setup.

    To get the most correct answer, I recommend opening a new thread in the Microsoft Fabric Community, specifically under the Power BI forum. This space is actively followed by Microsoft MVPs, platform developers, and experts who regularly work with Dataverse and Project data in Power BI. Beyond standard troubleshooting, the forum provides access to a vast repository of community-tested templates and deep-dive technical documentation that addresses complex issue. Participating in this forum can also be a great opportunity to learn from experts who solve these scenarios daily and further refine your approach. Your current post is already well structured, so you can reuse it, including the list of tables you can see and the custom fields you're missing.

    I hope you find a setup that gives you the live dashboard you need. Thank you for your patience and understanding. Wishing you all the best.

    Was this answer helpful?

    0 comments No comments

  2. AI answer

    2026-11-12T15:26:45.3566667+00:00

    Planner Premium’s built-in local custom fields are stored in binary form inside the Project scheduling data and are not exposed as columns or a supported relational table for Power BI; for live reporting, create separate reportable Dataverse fields and move future data entry to those fields. ^1^

    What is happening

    • Premium plans and tasks are stored in Dataverse and managed through the former Project for the web service. ^2^
    • Standard task data is available through tables such as msdyn_projecttask.
    • Fields created through Planner’s Add new field experience are local custom fields. Their definitions and values are held in binary scheduling data, not ordinary Dataverse columns, and Microsoft states that they are unavailable for reporting. ^1^
    • Therefore, there is no additional supported Dataverse table that can simply be joined to msdyn_projecttask to retrieve those local values.

    First verify each listed field. For example, if Description is actually Planner’s standard notes field rather than a field created with Add new field, it may already be available as task notes. The documented project export model includes notes and unformattednotes as standard task properties, while custom-field values are represented separately by field GUID. ^3^

    API support matrix

    Method Native Planner-local custom fields
    Power BI Dataverse connector Not exposed as reportable columns
    Dataverse Web API/TDS Cannot turn the binary local fields into a supported relational dataset
    Microsoft Graph v1.0 Planner API Not supported for this Premium custom-field scenario
    Microsoft Graph beta plans_v2 Custom-field resources are documented, but beta is unsupported for production
    Project Schedule APIs Support explicit Dataverse custom fields on scheduling entities; they do not provide a reporting projection of Planner-local binary fields

    The Graph beta endpoint documents task custom-field values, but the permissions table currently says delegated and application permissions are all Not supported. Beta APIs are also explicitly unsupported for production applications. ^4^

    Project Schedule APIs support out-of-box and custom fields for scheduling entities, including Project Task. That applies to explicit Dataverse custom columns—not Planner-local fields embedded in the binary schedule payload. ^5^

    This requires a Dataverse Environment Maker/System Customizer or administrator, plus permission to publish the Power BI semantic model. If those roles are unavailable, provide these steps to the Power Platform administrator.

    1. Confirm the environment
      • In Power Platform admin center, identify the Dataverse environment containing the Premium plan—currently the stated GMR Holdings Private Limited (default) environment.
      • Confirm that msdyn_project contains the plan before creating anything.
    2. Create reportable storage
      • In Power Apps maker portal, select that environment.
      • Go to Solutions → New solution.
      • Add a custom table such as Planner Task Reporting Fields.
      • Add a required lookup to Project Task (msdyn_projecttask).
      • Add typed columns for Scope, Skill Code, Task Reference, Remarks, and Day Wise Tracking. Use Choice, Text, Number, or Date columns as appropriate.
      • Make the Project Task lookup unique if each task should have only one reporting row.
      A related table is preferable unless adding columns directly to msdyn_projecttask has been validated for this Planner environment. It keeps reporting customization separate from Microsoft-managed scheduling entities. Microsoft documents related custom tables as a supported simple customization pattern. ^6^
    3. Provide an editing interface
      • Add the custom table and fields to a model-driven Power App form.
      • Grant users Dataverse security-role permissions to read/write that table and reference Project Task records.
      • Users must maintain these new values through this app or another Dataverse-backed interface.
      Existing Planner-local fields will not synchronize automatically. Future data entry must move to the new Dataverse fields.
    4. Build Power BI
      • Connect using Get data → Power Platform → Dataverse.
      • Load msdyn_project, msdyn_projecttask, the custom reporting table, and required bucket/label tables.
      • Relate the custom table’s Project Task lookup to the task primary key.
      • Use DirectQuery for near-real-time reporting and automatic page refresh, understanding that it can be slower.
      • Use Import for better performance when scheduled latency is acceptable. Import models require refresh; DirectQuery can provide near-real-time results. ^7^

    Existing values

    Historical local-field values require a one-time migration. The documented ExportProjectContent output includes custom-field definitions and task values keyed by GUID, so investigate whether the applicable export tooling and permissions are available for your environment. ^3^

    That export is a migration input, not a supported live Power BI interface. If the tool is unavailable, the remaining supported route is one-time re-entry or an administrator-approved migration into the new Dataverse table.


    References

    1. Frequently Asked Questions
    2. Manage the Planner app for your organization in Microsoft Teams
    3. Export Project Content Definition
    4. List customFieldValues
    5. Project schedule API performance
    6. Licenses for customizations of Project for the web
    7. Power BI modeling guidance for Power Platform
    AI-generated content may be incorrect. Read our transparency notes for more information.

    Was this answer helpful?